Subject: Reservoir operation Posted: 5/15/2013 Viewed: 24674 times
Hi Mr. Jack
How can I control on discharge from the reservoir ?
kind regards
Aumran Nazar
Mr. Jack Sieber
Subject: Re: Reservoir operation Posted: 5/15/2013 Viewed: 24670 times
WEAP will release water from a reservoir if the level is above the Top of Conservation level, or if there is a hydropower demand, or if there is a downstream demand for it (either an instream flow requirement or a withdrawal for a demand site). The demands must have a higher priority than the reservoir's priority for filling. Also, a reservoir cannot release water below its Top of Inactive level.