Subject: Scenarios
Posted: 4/4/2010 Viewed: 36597 times
Is it Posible to run two or more scenarios with different start and end years, for instance having a scenario running from 1990-2009 and another one runing from 2009-2030,if so how can this be carried out in WEAP?
Regards Nes |
Subject: Re: Scenarios
Posted: 4/4/2010 Viewed: 36585 times
This is not possible in WEAP. Every scenario must have the same start and end years.
|